DEMOCRATIC SOCIALIST REPUBLIC OF  SRI LANKA

AERONAUTICAL INFORMATION SERVICES (AIS/HQ)

AIRPORT& AVIATION SERVICES (S.L.)(PRIVATE) LTD

          BANDARANAIKE INTERNATIONAL AIRPORT   COLOMBO

     KATUNAYAKE, SRI LANKA

AIC

A01/22

20 MAY

SERIES "A"

INTERNATIONAL

 

CONSTRUCTION OF NEW TERMINAL BUILDING, ASSOCIATED NEW PIER BUILDINGS AND PASSENGER BOARDING BRIDGES (PBB) AT BANDARANAIKE INTERNATIONAL AIRPORT (VCBI)

 

1.        Introduction

 

1.1      The purpose of this AIC is to inform all aircraft operators about the construction of the new terminal building (T2) ,associated new pier buildings and Passenger Boarding Bridges (PBB) at Bandaranaike International Airport under the BIA Development Project Phase II Stage 2.

 

1.2      The project will address issues such as congestion and passenger discomfort at the airport. Accordingly the new terminal is expected to handle nine million passengers annually, taking the airport’s passenger handling capacity to fifteen million passengers annually.

 

1.3      The project will involve the construction of a new multi-level terminal building with a floor area of approximately 180,000 square meters, two new piers,16 PBBs and a connecting concourse link to the existing terminal (T1). In terminal 2 (T2) the arrival and departure terminal areas will be separated vertically.

 

( Refer Appendix A for Aerial view of the new developments )

 

( Refer Appendix B for Airside Layout of the new developments )

 

 

2.                          Scope of the BIA Development Project Phase II Stage 2    

2.1.     New passenger terminal building (T2) including new pier (Pier 2) with 8 PBBs connecting concourse link to the existing terminal building (T1)

 

2.2.     New pier (Pier 3) with 8 PBBs connecting concourse link to the new passenger terminal building (T2)

 

2.3.     Multi storey car park

 

2.4.     Elevated roadway

 

2.5.     Public utilities and solid waste disposal system.

 

3.                          Comparison of facilities between Existing Terminal (T1) with New Terminal (T2)

Facility

Existing Terminal(T1)

New Terminal (T2)

Total on completion

Capacity of the terminal

6 Million Passengers Per Annum

9  Million  Passengers  Per Annum

15  Million  Passengers  Per Annum

Floor area

90,000M2

180,000M2

270,000M2

Check-in counters

53 Numbers

96 Numbers

149 Numbers

Departure passport control counters

21 Numbers

32  Numbers

53  Numbers

Airside security control positions

8 Positions at Pier 1

2 Positions at bus gate

20 Positions at Pier 2 and Pier 3

28 Positions at Pier 1, Pier 2 and  Pier 3

2 Positions at bus gate

                                                                                                                                                             Contd.

 

Facility

 

Existing Terminal(T1)

New Terminal (T2)

Total on completion

Contact gates

8  Numbers

16  Numbers

24  Numbers

Bus gates

6  Numbers

10  Numbers

16  Numbers

Airline lounges

4  Numbers

 6  Numbers

10  Numbers

Arrival passport control counters

27  Numbers

56  Numbers

83  Numbers

Baggage claim carousels

6  Numbers

7  Numbers

13  Numbers

Baggage Mark-up carousels

3  Numbers

7  Numbers

10  Numbers

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.    Date of Completion

4.1.     Construction activities have already been commenced and expected to be completed by end of December 2023.   

5.    Applicability

5.1.     Existing AD Chart in the AIP Page VCBI AD 2-35 and other information related to upgrade of facilities will be updated in the AIP on the completion of the project.

       Capt. THEMIYA ABEYWICKRAMA

    DIRECTOR GENERAL OF CIVIL AVIATION & CEO

    CIVIL AVIATION AUTHORITY OFSRI LANKA

 

                                                                                    (END of AIC )